Construction of the two combustion turbine-generators are financed by existing funds on hand by GIUD and bonds approved by the Grand Island City Council. Grand Island Utilities Department electric rates are not anticipated to increase in order to complete the project. Electric customers in Nebraska pay some of the lowest electric prices in the nation. GIUD customers enjoy some of the lowest electric rates in Nebraska.
|
| Construction of the foundations for the two gas turbines are progressing ahead of schedule. Shown in the foreground is the foundations for unit GT-2. The foundations for unit GT-3 is shown just to the upper left of the yellow crane. Both units are manufactured by General Electric in France. Date: 2-28-02 | |
![]() |
Shown to the left is the construction site in April 2002. Both generators are set in place and the site is ready to receive the combustion turbines. |
| Date: 4-19-02 |